S1 - Lowering In The DRUPS Rooms Walls
Monday, 06 August 2012 17:48

Things are still progressing well in Sydney this week. Today we've been lowering the pre-cast concrete DRUPS room walls down into the lower ground level. If you read the blog on Friday you would have seen the space we left in the ground level specifically for this task.

Once the walls have been lowered into place, we will be installing the additional formwork ready to complete the ground level pour.

In this second photo you can see the area to the right ready to be poured. We've held off on this last area of the slab so that the DRUPS room walls would not be effected. Over the coming week we'll be showing you some photos of what's left of the pour. Level 1 is getting very close!

Check back with us tomorrow to see a very impressive looking M1.

 

Comments  

 
0 #2 NEXTDC 2012-08-07 12:40
Hi Matt, you can rest assured P1 is still going ahead. At the moment we're finalising the construction plans so we can begin soon. We will have more on the blog once we make an announcement to the market.
Quote
 
 
+1 #1 Matt 2012-08-06 21:43
Hi Folks,

Where's the love for P1? No updates, no news, no construction progress for months... please tell us it's still happening!